Pre-construction condition survey: proof of damage starts before the work
With a pre-construction condition survey (bouwkundige vooropname), you record the condition of nearby buildings before construction or demolition. That way, you can later separate existing damage from damage that arises during or after the work.
How a pre-construction condition survey works
Choosing buildings and making appointments
First, it is decided which buildings get a survey. Think of the houses next to a new excavation on Kerkstraat. Then you make appointments with the owners or occupants. If someone does not respond, ProRail's PHS Den Bosch-Vught project (ProRail manages the Dutch rail network) only surveys the outside, from the public road.
Recording the inside and the outside
You describe and photograph the inside and the outside of the building. You record existing damage, such as a crack in a wall, with a description and a photo. That way, it is clear later what was already there.
Drawing up the report
You turn the survey into a report. The owner can receive that report. In the ProRail project PHS Den Bosch-Vught, the report is ready within 2 weeks of the last survey day.
Surveying again and comparing
During the work, a new survey may follow, for example per project phase. Rijkswaterstaat (the Dutch public works agency) describes it like this: first a baseline measurement, then repeats. If someone reports damage, you compare the new condition with the pre-construction survey.
What is a pre-construction condition survey?
A pre-construction condition survey records the condition of a building before construction or demolition takes place nearby. Other names are nulmeting and nulopname (baseline survey).
It can concern homes and commercial buildings. You describe and photograph the inside and the outside. The aim: to separate existing damage from damage that arises later.
A building inspection looks at defects, costs and timeframes. A pre-construction survey mainly records the state of the building at that moment.
Why do you make a pre-construction survey before the work?
If damage arises during the work, the question is what was already there. A pre-construction survey answers that, with a date and photos.
ProRail explains: anyone who thinks train vibrations caused damage must, under the law, prove that ProRail is the cause. An in-depth investigation includes a baseline measurement, photos and vibration measurements of at least a week.
Rijkswaterstaat names two aims for surveys in projects. First: checking whether objects in the surrounding area remain intact. Second: in case of damage, establishing its extent, for compensation.
What does the SBR vibration guideline (part A) say?
Can vibrations damage a building? In the Netherlands, this is assessed with SBR guideline A, Schade aan bouwwerken (damage to buildings). That is what ProRail's damage protocol states.
The guideline describes how to measure vibrations on a building. It also sets out how to assess the result, with limit values for vibration velocity and vibration acceleration.
Part A was revised in November 2017 by SBRCURnet. The previous version dated from 2002, with a reissue in 2006. SBRCURnet ceased to exist at the end of 2017. CROW took over the guidelines.
New in 2017 is a checklist for the structural condition. With it, you determine whether a building is sensitive to vibrations. According to ProRail, this classification is mainly based on what you can see on the building.
Do the vibrations stay below the limit values? In ProRail's damage protocol, the chance of damage from train vibrations is then less than 1%.
The guideline is not a law. For construction and demolition work, the Bbl does refer to part B, for nuisance in a habitable area (art. 7.18). The three parts:
- Part A: damage to buildings (revised in November 2017)
- Part B: nuisance to people in buildings (the Bbl names the 2006 version)
- Part C: disturbance of equipment
Is a pre-construction condition survey mandatory?
Anyone who builds must take measures against danger to surrounding buildings and land. That is stated in article 7.15 of the Besluit bouwwerken leefomgeving (Bbl, the Dutch building regulations).
A risk matrix gives a risk score. From 12 points, a construction safety plan (bouwveiligheidsplan) is mandatory. That plan is submitted with the building notification (bouwmelding) or the permit application.
For an excavation, that plan also contains starting points for a monitoring plan. It must prevent danger to adjoining buildings (belendingen), that is, the buildings next door.
The central government's explanation on IPLO (its information point for building rules) does not mention the pre-construction survey itself. So check per project what the assignment or contract says.
Who commissions the survey, and who carries it out?
That differs per project. Two examples from official sources show how it can work.
Take ProRail's rail project PHS Den Bosch-Vught. A specialised firm makes the appointments there, carries out the surveys and writes the reports. ProRail pays; the owner pays nothing.
In Rijkswaterstaat projects, the contractors carry out the building surveys and the monitoring. Rijkswaterstaat does not prescribe a fixed method for this.
There is an assessment guideline (beoordelingsrichtlijn) for pre-construction condition surveys: BRL 5024. A KOMO process certificate (a Dutch quality certificate for construction) is based on it. If you want that certificate for your firm, first check which version of BRL 5024 currently applies.
What is in a good pre-construction survey report?
The report must later show the state the building was in. ProRail describes it like this: you record the inside and the outside, in text and with photos.
There is no fixed method. Rijkswaterstaat, for example, does not prescribe one.
But a colleague must be able to find the same spots again in a later survey. This way of working helps with that. It is advice, not a rule:
- Address and date of the survey
- The inside and the outside, per room and per facade
- All existing damage, with a description and a photo
- For a crack: the location and the dimensions
- What could not be inspected, and why
What do you run into in practice?
A large project involves many addresses at once. That puts pressure on the planning and on the delivery time. Watch out for these points:
- Many appointments with occupants in a short time
- No response: for PHS Den Bosch-Vught, then only a survey from outside
- A short delivery time: for PHS Den Bosch-Vught, within 2 weeks
- More surveys per project phase, which you must be able to compare
- The report may become evidence in a damage claim
What can Keursnel do now, and what comes later?
The pre-construction condition survey is listed in Keursnel as “Binnenkort” (coming soon). You cannot create a pre-construction survey yet. We do not give a date or features yet.
Do you do pre-construction surveys? Tell us via the contact page that you are interested, and what you need.
Right now, you only do the building inspection in Keursnel. It already includes:
- Photos with arrow, circle, numbered marker or measuring line
- The time taken, from the photo itself; the original never changes
- Built to work without internet: your work waits, encrypted, on your device
- Team and roles: main admin, manager and team member
- Your own house style in the report, with a paid plan
- A fixed report version with a checksum, to share via a link you can revoke
Frequently asked questions
What is the difference between a pre-construction survey and a baseline measurement?
With both, you record the condition before the work starts. ProRail treats a building survey as the same as a nulopname (baseline survey). Rijkswaterstaat speaks of a nulmeting (baseline measurement), followed by repeats.
Is a pre-construction condition survey mandatory?
The central government's explanation of safety during building work does not mention the pre-construction survey itself. But anyone who builds must take measures against danger to surrounding buildings. So check per project what the assignment or contract says.
Who pays for the pre-construction survey?
That depends on the project. In ProRail's PHS Den Bosch-Vught project, ProRail pays for the surveys, and the owner pays nothing. Agree this in advance with your client.
What do you do if an occupant does not respond?
In ProRail's PHS Den Bosch-Vught project, only the outside is then surveyed, from the public road. State in the report that the inside was not inspected, and why. Then it is clear later what the survey does and does not show.
What is BRL 5024?
BRL 5024 is an assessment guideline for carrying out pre-construction condition surveys. A KOMO process certificate is based on it. If you want the certificate for your firm, first check which version currently applies.
Can I do this in Keursnel now?
No, not yet: the pre-construction condition survey is listed in Keursnel as coming soon. You cannot create a pre-construction survey yet, and we do not give a date yet. Right now, you only do the building inspection in Keursnel. If you are interested, tell us via the contact page.
See also
New-build handover inspection
Handover of new builds under the Wkb: proces-verbaal, 5% rule and repairs; not yet available in Keursnel.
Photos
Add photos per item, point things out in the editor and show them in the report.
Report
The report builds itself as you inspect: 13 parts, ready to share online and to print.
Building inspection
Inspect the home from roof to crawl space and deliver the report with costs and NHG annex.
See pricing
Free for 3 reports a month. After that €25 per inspection, or from €7.50 per inspection with a subscription. All prices exclude VAT.
Inspect without the hassle afterwards
Record the inspection on site. Keursnel works out the costs and creates the report with the NHG annex.